The West Grand project is well underway. The following is a tentative timeline for the rest of the project.
Undercut cul-de-sac 9/16 thru 9/17
Misc. grading 9/18 thru 9/19
Valley Gutter 9/19 thru 9/20
Driveways 9/23 thru 9/26
Topsoil & final grading behind curbs 9/26 thru 9/27
Aggregate base course 9/30 thru 10/02
Asphalt paving 10/03 thru 10/04
Seeding 10/07 thru 10/08