The West Grand project is well underway. The following is a tentative timeline for the rest of the project.

Undercut cul-de-sac                            9/16 thru 9/17

Misc. grading                                        9/18 thru 9/19

Valley Gutter                                         9/19 thru 9/20

Driveways                                            9/23 thru 9/26

Topsoil & final grading behind curbs     9/26 thru 9/27

Aggregate base course                        9/30 thru 10/02

Asphalt paving                                    10/03 thru 10/04

Seeding                                              10/07 thru 10/08