Tentative Street Work Schedule

Friday 9/23/22  – Milling and Patching of Leonard St.

Monday 9/26/22 – Chip Seal application to Leonard St.

Thursday 9/29/22 – Microsurfacing of the following Streets

1. Maple Ave from Park Ave to 1st Evergreen Ct. entrance.

2. Thayer Ave.

3. S. Lincoln Ave from Urban to Wabash

4. W. Glenn Ave from Leonard St to Fillmore

5. Homewood Ave. from Leonard St. to Fillmore

Friday 9/30/22- Microsurfacing the following Streets

1. W. Glenn Ave from Leonard St. to Welch St.

2. Homewood Ave. from Leonard St. to Welch St.

3. Urban Ave.

4. Maple Ave. from the west Evergreen Ct. entrance to MacArthur Blvd.

Monday 10/3/22 – Microsurfacing the following streets

1. Leonard St.

2. Welch St.

Schedule is dependent upon weather. Residents will be notified day before work is started on their street. Please remove all vehicles, garbage cans, etc from street or gutter prior to work starting. Notify any contractors, deliveries to reschedule.

Important Street Repair Information

Starting September 22nd, 2022 (weather dependent) the Village of Jerome will be conducting Street Restoration Projects throughout the Village.
Streets will be closed periodically and for multiple hours during the day while work is completed.
Once a Street is barricaded off absolutely NO access will be allowed unless it’s an Emergency!
Closures will average 3 to 4 hours each.
The schedule is as follows: (weather dependent)
9/22/22- Patching of Leonard St. Starting 700 AM, may be pushed to 9/23/22
9/23/22 or 9/26/22- Chip Sealing of Leonard St. Start time 700AM
9/27 through 9/30/22 – Micro surfacing of the following Streets

  1. Welch St.
  2. Homewood Ave.
  3. W. Glenn Ave. (from Welch St. to Fillmore Ave.)
  4. Leonard St.
  5. Maple Ave.
  6. Urban Ave.
  7. Thayer Ave.
  8. S. Lincoln Ave. (from Urban to Wabash Ave.)

    Please follow posted signs and closures and adjust accordingly.
    More information will be posted on the Village of Jerome website.
    Any Questions should be directed to Public Works directly at 217-546-9647.

Leonard St. Road Work (UPDATED)

ATTENTION Village of Jerome residents on Leonard St.:

 Starting Thursday September 22nd, 2022 at 7:00 AM The Village of Jerome has hired a contractor to mill and patch several areas on Leonard St. in conjunction with a chip seal application. This activity will take place over two days. Please refrain from parking on Leonard St. on 22nd and 23rd.

Following the patching of Leonard St., a chip seal will be applied to the entirety of Leonard St. from Wabash Ave. to Iles Ave. During the chip seal application no traffic will be allowed on Leonard St. until the chips have been firmly pressed into the oil. This process is called “cape sealing”, and is the first step in completing a microsurfacing project that is tentatively scheduled to begin on September 26th, 2022. More information on the microsurfacing project will follow shortly.All cars MUST be off the street prior to application of the chip seal or they will be towed at owners expense.

NOTE: This article was updated 9/20 at 8:26am due to weather delaying the project.

yellow payloader

Street Sweeping

The Village of Jerome Public Works Department will be Street Sweeping starting Monday Sept. 19th through Friday the 23rd, 2022 

ALL vehicles will need to be removed off the following streets from 7:30 am to 3:00 pm. 

Homewood Ave, Glenn Ave, Welch St, Leonard St, Fillmore, Maple Ave, Urban Ave, Lincoln Ave, Thayer Ave, Calland Dr., W. Grand Ct, Alberta Ln, Reed Ct, Barbara Ct, Homewood Ct, And Jerome Ave from Corbin to Chatham Rd.