Friday 9/23/22  – Milling and Patching of Leonard St.

Monday 9/26/22 – Chip Seal application to Leonard St.

Thursday 9/29/22 – Microsurfacing of the following Streets

1. Maple Ave from Park Ave to 1st Evergreen Ct. entrance.

2. Thayer Ave.

3. S. Lincoln Ave from Urban to Wabash

4. W. Glenn Ave from Leonard St to Fillmore

5. Homewood Ave. from Leonard St. to Fillmore

Friday 9/30/22- Microsurfacing the following Streets

1. W. Glenn Ave from Leonard St. to Welch St.

2. Homewood Ave. from Leonard St. to Welch St.

3. Urban Ave.

4. Maple Ave. from the west Evergreen Ct. entrance to MacArthur Blvd.

Monday 10/3/22 – Microsurfacing the following streets

1. Leonard St.

2. Welch St.

Schedule is dependent upon weather. Residents will be notified day before work is started on their street. Please remove all vehicles, garbage cans, etc from street or gutter prior to work starting. Notify any contractors, deliveries to reschedule.